The contractor shall provide all qualified personnel, transportation, tools, equipment, materials and services required to prep and repaint Heritage Park flag pole and concrete base on Little Rock AFB, AR 72099. The contractor shall accomplish all services below to meet the requirements of this Performance Work Statement (PWS). Work shall be in compliance with all Federal, State and local regulations, codes and license requirements. Work shall be accomplished within 30 days of material arrival. Estimated delivery date of material is required to be sent to the Contracting Officer Representative (COR) within 15 days of contract award. Work shall be completed within 90 day of award.The contractor shall perform full prep of the metal flag pole and the concrete base surrounding the pole. Prep includes sanding or sand blasting the pole to eliminate any rough areas or chipped areas. Concrete base area is 43 feet 6 inches in dia
↧